Hello, dear friend, you can consult us at any time if you have any questions, add WeChat: THEend8_
Topic: Bills of Quantities for Preliminaries and Groundworks
Weight: 35%
Type: Individual Report
TASKS
Students are required to prepare Bills of Quantities (BOQ) including preliminaries and groundworks for the given drawings on the applicable project and scope, in accordance with the Australian and New Zealand Standard Method of Measurement for Building Works (ANZSMM).
Table 1: Project and scope for each student
Last Digit of Student ID |
Scope |
0, 1, 2 |
Project A (2 units between Grids 1-4 and Grids AX-EX) |
3, 4 |
Project A (2 units between Grids 7-9 and Grids AX-GY) |
5, 6, 7 |
Project B (Unit between Grids 1-4 and Grids A-J) |
8, 9 |
Project B (Unit between Grids 4-7 and Grids A-J) |
You are required to compile the take-off list, measurement sheet, query sheet and BOQ. (Hint: For preliminaries, no need to prepare, take-off list, measurement sheet and query sheet). Please use the templates provided in MyUni. Please note that you are NOT required to price the BOQ. Pricing is taught in a different course.
Recommended procedure:
First, you need to identify the items that should be measured for Groundworks using the take-off sheet, while referring to the given project drawings and ANZSMM.
Next, take-off quantities for those identified items using the measurement sheets, following measurement rules in ANZSMM and referring to project drawings and specifications.
Use query sheet to mention the queries/assumptions made on missing details/ discrepancies. In the query sheet, both columns should be filled. That is the query and your assumed answer.
BOQ for Preliminaries and Groundworks – For Groundworks BOQ, use the quantities you measured in the measurement sheets, also remember to add appropriate ‘preamble notes’ and ‘trade preliminary items’ before those measured items to make a complete BOQ. Preamble notes and trade preliminary items are listed at the beginning of each ANZSMM section. For Preliminary BOQ, include minimum 8 preliminaries that are applicable to the given drawing.
WORD LIMIT
It is inappropriate to strictly impose a word limit to this type of submission. You are required to provide all required components as advised in the Assessment brief irrespective of the word count as one report.